Ripa Ladrang Foundation Home | Purpose | Contact | Membership 

 
Ripa Ladrang Home
 
About Ripa Ladrang
  * News
  * Meet the Ripa Teachers
  * Teaching Schedule
  * Sangha Meetings
  * Divinations
  * Prayers
  * News Archive
 
Special Projects
  * Monk Sponsorship
  * New Treasures Project
  * Compassionate Projects
 
 
Photo Journals
  * New Treasures Photo Journal
  * India, Feb. 2001
  * Asian Pilgrimage 1999
  * Photo Gallery
 
Special Info
  * Inspiration
  * Sacred Stories
  * The Meaning of Sangha
  * Tibetan Medicine
 

       
   

Monastery Complex, Dallu, Pharping

Progress Status as of May  2003

S. No. Activities Status
1.

RCC Casting Work

All the Major Casting Works completed.

2.

Brickwork   

97%, except brickwork at Main Door of Ground Floor.

3.

Cement Plastering

98%, except Plastering work for Ground Floor Main Door.

4.

Articulation works with Cement Plaster Carvings on Beams, Walls & Column Capitals

95% Complete, except the Pema-Chicha of Windows

5.

Wood Works

80% Complete

6.

Plaster of Paris Finishing on inside walls

Complete with cornice fitting

7.

Ceramic Tile Fitting

Almost complete except fixing of Floor tiles in Kitchen.

8.

Steel Handrail Fitting

Fitting complete at Staircase hall, Staircase of First. 

9.

PCC Articulated Railings Fitting

Complete

10.

Steel Staircase at Second Floor

Fitting complete

11.

Water Supply & Sanitary Works

Almost complete except fixing of fixtures

12.

Electrical Works

90% Complete, with wire pulling and Switch Box Fitting,

except Lamp and Switch Fittings

MISCELLANEOUS

2.1 Man Power

We have mobilized adequate manpower as per the job requirement which includes technical, non-technical and supporting staffs. The detail is shown in Appendix-A.

2.2 Materials

We have already stockpiled adequate quantity of construction materials at the site for the execution of the works, without hampering our work  and we are still procuring the materials. The detail of construction materials brought during the progress period is shown in Appendix-A.

2.3 Equipment

The list of equipments mobilized during the progress period as per the  requirements of jobs is shown in Appendix-A.

Appendix-A

Manpower Mobilized During the Progress Period

S. No.

Name

Designation

Remarks

1.

Mr. Swarup G. Koney

Architect

 

2.

Mr. Sanjay Gurung

Civil Engineer

 

3.

Mr. Santosh Mishra

Resident Overseer

 

4.

Mr. Shyam Lama

Supervisor

Civil Works

5.

Mr. Chitra Bahadur Lama

Supervisor

Civil Works

6.

Mr. Babu Lama

Supervisor

Articulation Works

7.

Mr. Shyam Lama

Supervisor

Civil Works

8.

Mr. Sakaldev Chaudhary

Supervisor

Electrical Works

9.

Mr. Bharat Sharma

Supervisor

Wood Works

10.

Mr. Ram Dangol

Supervisor

Water Supply and Sanitary Works

11.

Mr. Shambhu Amgain

Supervisor

Waterproofing Works

12.

Mr. Hari Sharma

Supervisor

Painting Works

Trades Men Mobilized During the Progress Period (Average)

S. No.

Description

Number

1.

Labours

95-115

2.

Masons

45

3.

Carpenters

16

4.

Bar benders

15

Materials Mobilized During The Progress Period

S. No.

Description

Specification

Quantity at site

Units

1.

Cement

Indian 53 G

9500

Bags

2.

Sand

River

2500

Trip

3.

Bricks

Local

6,00,000

Pcs.

4.

Aggregate

Crushed

1500

Trip

5.

Steel

Shakha

150

MT

Equipment, Tools and Plants Mobilized During The Progress Period

S. No.

Description

Size

Nos.

Remarks

1.

Concrete Mixer M/C

Single Bag Capacity

2

 

2.

Concrete Vibrator

Petrol

6

 
 

Electric

8

 

3.

Water Pump

1.5 Hp

1

 

4.

Water Pump

0.5 Hp

6

 

5.

E. Generator (Honda)

2 KVA

1

 

6.

Theodolite with Ranging staff

Standard

1

Wild Type

7.

Wheel Barrow

Standard

6

 

8.

Steel Props

6 mtr. (2” Dia)

1500

 

9.

Clamps

 

3000

Japanese, Indian, Chinese type

10.

U-Jack

 

1500

 

11.

Steel Plates

2’ x 4’

800

 

12.

Vertical Saw

1000 W

1

 

13.

Circular Saw

1500 W

1

 


New Treasures Photo Journal Links:

  • Groundbreaking Ceremony
  • August 2000
  • November 2000
  • December 2000
  • March 2001
  • April 2001
  • December 2001
  • Statue Renderings
  • January 2002
  • June 2002
  • May 2003
  • June 2003
  • Progress Report
  • July 2003