97%, except brickwork at Main Door of Ground Floor.
3.
Cement Plastering
98%, except Plastering work for Ground Floor Main Door.
4.
Articulation works with Cement Plaster Carvings on Beams, Walls
& Column Capitals
95% Complete, except the Pema-Chicha of Windows
5.
Wood Works
80% Complete
6.
Plaster of Paris Finishing on inside walls
Complete with cornice fitting
7.
Ceramic Tile Fitting
Almost complete except fixing of Floor tiles in Kitchen.
8.
Steel Handrail Fitting
Fitting complete at Staircase hall, Staircase of First.
9.
PCC Articulated Railings Fitting
Complete
10.
Steel Staircase at Second Floor
Fitting complete
11.
Water Supply & Sanitary Works
Almost complete except fixing of fixtures
12.
Electrical Works
90% Complete, with wire pulling and Switch Box Fitting,
except Lamp and Switch Fittings
MISCELLANEOUS
2.1 Man Power
We have mobilized adequate manpower as per the job requirement which
includes technical, non-technical and supporting staffs. The detail is
shown in Appendix-A.
2.2 Materials
We have already stockpiled adequate quantity of construction materials
at the site for the execution of the works, without hampering our work
and we are still procuring the materials. The detail of construction materials
brought during the progress period is shown in Appendix-A.
2.3 Equipment
The list of equipments mobilized during the progress period as per the
requirements of jobs is shown in Appendix-A.
Appendix-A
Manpower Mobilized During the Progress Period
S. No.
Name
Designation
Remarks
1.
Mr. Swarup G. Koney
Architect
2.
Mr. Sanjay Gurung
Civil Engineer
3.
Mr. Santosh Mishra
Resident Overseer
4.
Mr. Shyam Lama
Supervisor
Civil Works
5.
Mr. Chitra Bahadur Lama
Supervisor
Civil Works
6.
Mr. Babu Lama
Supervisor
Articulation Works
7.
Mr. Shyam Lama
Supervisor
Civil Works
8.
Mr. Sakaldev Chaudhary
Supervisor
Electrical Works
9.
Mr. Bharat Sharma
Supervisor
Wood Works
10.
Mr. Ram Dangol
Supervisor
Water Supply and Sanitary Works
11.
Mr. Shambhu Amgain
Supervisor
Waterproofing Works
12.
Mr. Hari Sharma
Supervisor
Painting Works
Trades Men Mobilized During the Progress Period (Average)
S. No.
Description
Number
1.
Labours
95-115
2.
Masons
45
3.
Carpenters
16
4.
Bar benders
15
Materials Mobilized During The Progress Period
S. No.
Description
Specification
Quantity at site
Units
1.
Cement
Indian 53 G
9500
Bags
2.
Sand
River
2500
Trip
3.
Bricks
Local
6,00,000
Pcs.
4.
Aggregate
Crushed
1500
Trip
5.
Steel
Shakha
150
MT
Equipment, Tools and Plants Mobilized During The Progress Period